100 YINSON HOLDINGS BERHAD SECTION 05 : OUR CAPITALS MANUFACTURED CAPITAL FPSO ANNA NERY OVERVIEW Activity Date Contract award/ Letter of Intent ("LOI") issued (effective date) 11 October 2019 Award shipyard contract 13 March 2020 Issue purchase order for long lead items 15 March 2020 Vessel arrival at shipyard 16 March 2020 Entered into definitive contract 23 March 2020 First steel cut at module fabrication yard 1 June 2020 Hazard and operability (HAZOP) study completed 27 July 2020 Completion of first drydocking 12 October 2020 Commencement of second drydocking 25 April 2021 Operations phase updates Yinson maintained strong operations and safety performance despite the various challenges brought about by Covid-19 pandemic in FYE 2021, as outlined below: t "DIJFWFE BWFSBHF UFDIOJDBM VQUJNF PG BOE BWFSBHF DPNNFSDJBM VQUJNF PG GPS UIF TJY BTTFUT UIBU XFSF JO operation in FYE 2021. t "DIJFWFE BWFSBHF ZFBS UFDIOJDBM VQUJNF PG GPS UIF BTTFUT UIBU XFSF JO PQFSBUJPO TJODF ':& t 4JHOJmDBOU SFTPVSDFT XFSF EFQMPZFE UP NJOJNJTF $PWJE SJTL PO CPBSE PVS BTTFUT BOE NBJOUBJO PVS nFFU VQUJNFT t 4FWFSBM $PWJE DBTFT XFSF EFUFDUFE PO CPBSE UXP PG PVS BTTFUT BOE XFSF TXJGUMZ BEESFTTFE 1FSGPSNBODF PG UIF BTTFUT were maintained. Covid-19: Yinson’s new normal, pg 69 AVERAGE FLEET TECHNICAL UPTIME FOR ASSETS THAT WERE IN OPERATION IN FYE 2021 Q1 Q2 Q3 Q4 FYE 2021 average FPSO Adoon 100% 100% 100% 100% 100% FPSO Abigail-Joseph N/A N/A N/A 99.1% 99.1% FPSO JAK 99.9% 100% 99.9% 100% 99.9% FPSO Helang 99.2% 99.9% 93.5% 99.6% 98.1% FPSO PTSC Lam Son 100% 99.9% 99.9% 100% 100% FSO PTSC Bien Dong 01 100% 100% 100% 100% 100% * FPSO Abigail-Joseph’s first full quarter of operations was Q4 FYE 2021. 5-YEAR AVERAGE FLEET TECHNICAL UPTIME FOR ASSETS THAT WERE IN OPERATION Q1 Q2 Q3 Q4 FYE 2017 99.9% 99.9% 99.9% 99.9% FYE 2018 100.0% 99.9% 99.7% 99.9% FYE 2019 99.9% 100.0% 100.0% 99.4% FYE 2020 100.0% 100.0% 100.0% 100.0% FYE 2021 99.8% 99.8% 98.7% 99.8%

RkJQdWJsaXNoZXIy NDgzMzc=